M25 widening warning

M25 Widening: Junctions 27 – 30 – sheet piling

The following works will be carried out on the clockwise side of the M25 near to Belhus Park, South Ockendon.

Monday 31 January to Friday 18 February

Preparation work in advance of sheet piling. In order to ensure that all works are carried out in a safe manner and in a bid to minimise congestion, all works will take place between 10pm and 4.30am Monday to Friday. The steel sheet piles and rig will be delivered at night in readiness for the sheet piling work.

Monday 14 February to Friday 4 March

Sheet piling work. All work will occur between 8am and 6pm.
All efforts will be made to minimise noise and other impacts from the works. The work will be carried out under Section 61 consents, which is an approval gained from the local authorities to carry out this work at this time.

If you have any further queries, please do not hesitate to contact the Community Relations Team by telephoning 01708 256000 or by email to: communityrelations27-30.m25@sbbjv.co.uk.

The M25 Junctions 27 to 30 widening project is being carried out by Skanska Balfour Beatty Joint Venture for Connect Plus working on behalf of the Highways Agency.